Biman Bandar metro completes building the diaphragm wall
RAILWAYS & METRO RAIL

Biman Bandar metro completes building the diaphragm wall

This week marked a significant development in the metro project at the airport. On May 3, the diaphragm wall's construction was completed, giving the Biman Bandar metro station a boost.

The diaphragm wall, which connects the Jai Hind Metro Station to the Netaji Subhash Chandra Bose International Airport (NSCBI) terminal building, is in the subway, according to city metro authorities.

The cage on the wall is 17.405 meters long. It is around four meters wide and weighs about 15 metric tons. According to Kolkata Metro Railway, a traffic rerouting near the Airport Volvo bus stop was necessary to allow for the wall's construction.

The Airport Authority of India and the Bidhannagar Commissionerate had to approve it. Following approval, a traffic halt was implemented from 10.30 p.m. on May 30 to 7.56 a.m. on May 3.

The wall's construction was completed by the morning of May 3rd.

See also:
Construction of diaphragm wall for underground airport tunnel begins
Afcons kicks off a tunnel boring device without a diaphragm wall


This week marked a significant development in the metro project at the airport. On May 3, the diaphragm wall's construction was completed, giving the Biman Bandar metro station a boost. The diaphragm wall, which connects the Jai Hind Metro Station to the Netaji Subhash Chandra Bose International Airport (NSCBI) terminal building, is in the subway, according to city metro authorities. The cage on the wall is 17.405 meters long. It is around four meters wide and weighs about 15 metric tons. According to Kolkata Metro Railway, a traffic rerouting near the Airport Volvo bus stop was necessary to allow for the wall's construction. The Airport Authority of India and the Bidhannagar Commissionerate had to approve it. Following approval, a traffic halt was implemented from 10.30 p.m. on May 30 to 7.56 a.m. on May 3. The wall's construction was completed by the morning of May 3rd. See also: Construction of diaphragm wall for underground airport tunnel begins Afcons kicks off a tunnel boring device without a diaphragm wall

Next Story
Infrastructure Urban

Mount Expands Tumkur Facility with New Automated Panel, PEB Lines

Mount Roofing & Structures Private Limited, one of India's fastest-growing manufacturers in PUF and a leading solutions provider across pre-engineered building (PEB) and polycarbonate sheets, simultaneously inaugurated its second fully automated continuous sandwich panel manufacturing line and a new PEB manufacturing plant at its integrated campus in Tumkur.The milestone expansion, part of a total investment of Rs 250 crore, marks a significant advancement in the company's commitment to engineered performance, manufacturing scale, and industrial growth. The integrated facility spans approx..

Next Story
Infrastructure Transport

India Becomes First to Produce Bio-Bitumen for Roads

India has become the first country in the world to commercially produce bio-bitumen for use in road construction, according to Road, Transport and Highways Minister Nitin Gadkari. Bitumen, a black and viscous hydrocarbon derived from crude oil, is a key binding material in road building, and the bio-based alternative is expected to significantly improve the sector’s environmental footprint.Addressing the CSIR Technology Transfer Ceremony in New Delhi, Mr Gadkari congratulated Council of Scientific and Industrial Research on achieving the milestone, noting that the initiative would help curb ..

Next Story
Infrastructure Urban

HILT Policy Seen Boosting Telangana Revenue Sharply

The Hyderabad Industrial Land Transformation (HILT) Policy is expected to generate around Rs 1.08 billion in revenue for the Telangana state exchequer, according to Deputy Chief Minister Bhatti Vikramarka Mallu. Speaking in the Telangana Legislative Assembly, he said the policy would be implemented within a six-month timeframe in a transparent manner, with uniform rules applicable to all stakeholders. Mr Vikramarka noted that without the HILT Policy, the state would have earned only about Rs 1.2 million per acre. Under the new framework, however, revenue is projected to rise sharply to Rs 70 ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App