Metro Eyes Airport Link After Chingrighata Breakthrough
RAILWAYS & METRO RAIL

Metro Eyes Airport Link After Chingrighata Breakthrough

Completion of girder launching at Chingrighata has revived hopes of faster progress on several stalled Kolkata Metro projects. Metro Railway is aiming for December 2026 to open the Beleghata to IT Centre section so Orange Line passengers can interchange with the Green Line at Sector V and reach Howrah Maidan. The authority is targeting December 2027 for extension of services to the airport.

Metro Railway chief public relations officer S S Kannan said the Chingrighata work removed a major bottleneck on the New Garia?Airport corridor and that girder launching finished three hours ahead of schedule, with traffic on the EM Bypass restored at five am. The Orange Line had been stalled for one and a half years at the crossing because elevated viaduct construction required prolonged traffic diversions that were not earlier granted. Permission for temporary blocks allowed work to start and officials said progress has resumed.

Officials said the work was carried out in two phases over successive weekends, with RVNL first completing a 28 metre span between piers 317 and 318 before bridging a 34 metre span between piers 318 and 319. On the Joka?Esplanade Purple Line, work around Park Street has reached an advanced stage but relocation of B C Roy Market at Esplanade remains a hurdle. The corridor could take another two to two and a half years before services reach Esplanade, planned as a major interchange for three metro lines and buses.

On the Airport?Barasat corridor, tunnelling has passed the airport station and work between the airport and Michael Nagar is progressing quickly, although land related issues towards Barasat persist and meetings have been scheduled to resolve them. Officials indicated the Barasat extension could take another three years. Kavi Subhash station is expected to reopen before Durga Puja after completion of technical civil engineering work, the closure having been imposed purely for passenger safety.

Officials said the Barrackpore Metro project remains sanctioned and RVNL is studying alignment options that are likely to favour an elevated solution. The Railway minister Ashwini Vaishnaw said on X that the 62 metre viaduct gap had been bridged and that final works were completed with night traffic blockades over two successive weekends, allowing the busy crossing to reopen three hours ahead of schedule.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Completion of girder launching at Chingrighata has revived hopes of faster progress on several stalled Kolkata Metro projects. Metro Railway is aiming for December 2026 to open the Beleghata to IT Centre section so Orange Line passengers can interchange with the Green Line at Sector V and reach Howrah Maidan. The authority is targeting December 2027 for extension of services to the airport. Metro Railway chief public relations officer S S Kannan said the Chingrighata work removed a major bottleneck on the New Garia?Airport corridor and that girder launching finished three hours ahead of schedule, with traffic on the EM Bypass restored at five am. The Orange Line had been stalled for one and a half years at the crossing because elevated viaduct construction required prolonged traffic diversions that were not earlier granted. Permission for temporary blocks allowed work to start and officials said progress has resumed. Officials said the work was carried out in two phases over successive weekends, with RVNL first completing a 28 metre span between piers 317 and 318 before bridging a 34 metre span between piers 318 and 319. On the Joka?Esplanade Purple Line, work around Park Street has reached an advanced stage but relocation of B C Roy Market at Esplanade remains a hurdle. The corridor could take another two to two and a half years before services reach Esplanade, planned as a major interchange for three metro lines and buses. On the Airport?Barasat corridor, tunnelling has passed the airport station and work between the airport and Michael Nagar is progressing quickly, although land related issues towards Barasat persist and meetings have been scheduled to resolve them. Officials indicated the Barasat extension could take another three years. Kavi Subhash station is expected to reopen before Durga Puja after completion of technical civil engineering work, the closure having been imposed purely for passenger safety. Officials said the Barrackpore Metro project remains sanctioned and RVNL is studying alignment options that are likely to favour an elevated solution. The Railway minister Ashwini Vaishnaw said on X that the 62 metre viaduct gap had been bridged and that final works were completed with night traffic blockades over two successive weekends, allowing the busy crossing to reopen three hours ahead of schedule.

Next Story
Infrastructure Transport

Noida Airport Fuels NCR Realty Growth

The start of commercial operations at Noida International Airport has recently emerged as a major trigger for real estate growth across Noida, Greater Noida and the Yamuna Expressway region. The airport is expected to improve regional connectivity and support the next phase of development in eastern NCR.The airport, inaugurated on 28 March, has begun passenger services, while cargo operations are also expected to strengthen its role as an economic and logistics hub. Its operationalisation is expected to reduce dependence on Delhi’s Indira Gandhi International Airport for residents and busine..

Next Story
Technology

thyssenkrupp and GlobalLogic Form AI Alliance

thyssenkrupp AG and GlobalLogic, a Hitachi Group company, have recently formed a strategic alliance to deploy autonomous robotics and Physical AI across heavy industry operations. The partnership aims to improve safety, reduce engineering bottlenecks and accelerate industrial transformation at scale.The alliance brings together thyssenkrupp’s industrial expertise with Hitachi’s innovation capabilities. It includes GlobalLogic, Method and Hitachi America R&D, creating a “Lab-to-Scale” pipeline that connects research, digital strategy, design and enterprise software engineering for i..

Next Story
Real Estate

Platinum Corp Launches Luxury Suites in Santacruz

Platinum Corp has recently launched Platinum Stellar: Bespoke Presidential Suites, a premium residential project in Santacruz West, Mumbai. The development is positioned as a boutique luxury offering for homebuyers seeking expansive layouts, privacy and personalised living experiences.Located on Main Avenue, the project has been designed as a low-density, high-end residential address with spacious homes starting from 2,500 sq ft and extending to full-floor residences. The project targets HNIs, business owners and legacy residents from the Bandra-Khar-Santacruz belt.Platinum Stellar has been de..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement