Metro Eyes Airport Link After Chingrighata Breakthrough
RAILWAYS & METRO RAIL

Metro Eyes Airport Link After Chingrighata Breakthrough

Completion of girder launching at Chingrighata has revived hopes of faster progress on several stalled Kolkata Metro projects. Metro Railway is aiming for December 2026 to open the Beleghata to IT Centre section so Orange Line passengers can interchange with the Green Line at Sector V and reach Howrah Maidan. The authority is targeting December 2027 for extension of services to the airport.

Metro Railway chief public relations officer S S Kannan said the Chingrighata work removed a major bottleneck on the New Garia?Airport corridor and that girder launching finished three hours ahead of schedule, with traffic on the EM Bypass restored at five am. The Orange Line had been stalled for one and a half years at the crossing because elevated viaduct construction required prolonged traffic diversions that were not earlier granted. Permission for temporary blocks allowed work to start and officials said progress has resumed.

Officials said the work was carried out in two phases over successive weekends, with RVNL first completing a 28 metre span between piers 317 and 318 before bridging a 34 metre span between piers 318 and 319. On the Joka?Esplanade Purple Line, work around Park Street has reached an advanced stage but relocation of B C Roy Market at Esplanade remains a hurdle. The corridor could take another two to two and a half years before services reach Esplanade, planned as a major interchange for three metro lines and buses.

On the Airport?Barasat corridor, tunnelling has passed the airport station and work between the airport and Michael Nagar is progressing quickly, although land related issues towards Barasat persist and meetings have been scheduled to resolve them. Officials indicated the Barasat extension could take another three years. Kavi Subhash station is expected to reopen before Durga Puja after completion of technical civil engineering work, the closure having been imposed purely for passenger safety.

Officials said the Barrackpore Metro project remains sanctioned and RVNL is studying alignment options that are likely to favour an elevated solution. The Railway minister Ashwini Vaishnaw said on X that the 62 metre viaduct gap had been bridged and that final works were completed with night traffic blockades over two successive weekends, allowing the busy crossing to reopen three hours ahead of schedule.

Completion of girder launching at Chingrighata has revived hopes of faster progress on several stalled Kolkata Metro projects. Metro Railway is aiming for December 2026 to open the Beleghata to IT Centre section so Orange Line passengers can interchange with the Green Line at Sector V and reach Howrah Maidan. The authority is targeting December 2027 for extension of services to the airport. Metro Railway chief public relations officer S S Kannan said the Chingrighata work removed a major bottleneck on the New Garia?Airport corridor and that girder launching finished three hours ahead of schedule, with traffic on the EM Bypass restored at five am. The Orange Line had been stalled for one and a half years at the crossing because elevated viaduct construction required prolonged traffic diversions that were not earlier granted. Permission for temporary blocks allowed work to start and officials said progress has resumed. Officials said the work was carried out in two phases over successive weekends, with RVNL first completing a 28 metre span between piers 317 and 318 before bridging a 34 metre span between piers 318 and 319. On the Joka?Esplanade Purple Line, work around Park Street has reached an advanced stage but relocation of B C Roy Market at Esplanade remains a hurdle. The corridor could take another two to two and a half years before services reach Esplanade, planned as a major interchange for three metro lines and buses. On the Airport?Barasat corridor, tunnelling has passed the airport station and work between the airport and Michael Nagar is progressing quickly, although land related issues towards Barasat persist and meetings have been scheduled to resolve them. Officials indicated the Barasat extension could take another three years. Kavi Subhash station is expected to reopen before Durga Puja after completion of technical civil engineering work, the closure having been imposed purely for passenger safety. Officials said the Barrackpore Metro project remains sanctioned and RVNL is studying alignment options that are likely to favour an elevated solution. The Railway minister Ashwini Vaishnaw said on X that the 62 metre viaduct gap had been bridged and that final works were completed with night traffic blockades over two successive weekends, allowing the busy crossing to reopen three hours ahead of schedule.

Next Story
Infrastructure Energy

Batliboi Wins Rs 520 Mn Contract For Solar Cell Pollution Controls

Batliboi Limited has secured a major contract from SAEL Industries Limited to supply pollution control systems for a new solar cell manufacturing facility at Jewar in Uttar Pradesh. The order instructs Batliboi Limited's EEG Division to design, engineer, supply, install and commission a PEX system to support SAEL Industries Limited's six GW solar cell line. The contract is domestic in origin and was submitted to the stock exchanges under regulatory disclosure requirements. The contract value is Rs 520 mn, reflecting a substantial order for environmental control equipment for the manufacturing ..

Next Story
Infrastructure Urban

Delhi Approves PARIVARTAN Scheme To Replace Old Trucks And Buses

The Delhi government has approved the Programme for Accelerated Renewal and Incentivisation of Vehicle Assets for Reducing Transport Air Pollution and Network Emissions (PARIVARTAN) to cut transport-related emissions in the national capital. The scheme, supported by the Ministry of Road Transport and Highways (MoRTH), will phase out old, polluting trucks and buses and replace them with BS-VI, higher-emission-standard or electric vehicles. The initiative is intended to modernise the commercial vehicle fleet and strengthen the capital's clean transport system. Owners of Light Goods Vehicles that..

Next Story
Infrastructure Urban

Delhi Approves 2,800 Electric Buses Under PM E-DRIVE

The Delhi Cabinet has approved the induction of 2,800 air-conditioned, low-floor electric buses under the first phase of the Centre's PM E-DRIVE scheme, with the first vehicles expected from April 2027. The fleet is expected to be integrated into the city's public transport network by August 2028 and will move the government towards a target of around 14,000 buses by 2028-29. The Centre will provide assistance of up to Rs 3.5 million (mn) for each 12-metre bus and Rs 2.5 million (mn) for every nine-metre bus. Of the approved buses, 1,400 will be nine metres long and 1,400 will be 12-metre vehi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement