IPSCDL Completes Final Surfacing of Central Panaji Roads
SMART CITIES

IPSCDL Completes Final Surfacing of Central Panaji Roads

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.

Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.

From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.

St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.

IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.

Source:Goemkarponn

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.Source:Goemkarponn

Next Story
Infrastructure Urban

Naidu Seeks Rs 563 Crore For AP Sports Infrastructure

Andhra Pradesh Chief Minister N Chandrababu Naidu has sought Rs 563 crore from the Centre to boost sports infrastructure in the state, including Rs 538 crore for stadium development and Rs 25 crore to host the Khelo India Martial Arts Games 2025. Naidu made the request during a meeting with Union Youth Services and Sports Minister Mansukh Mandaviya in New Delhi on Wednesday.The CM urged early completion of Khelo India infrastructure projects in Tirupati, Rajahmundry, Kakinada, and Narasaraopeta, and called for an international-standard badminton training centre and a national aquatic sports hu..

Next Story
Infrastructure Transport

Tough Bidding Norms Slow NHAI Road Project Awards

Stringent bidding rules imposed by the Ministry of Road Transport & Highways (MoRTH) have led to a slowdown in project awards by the National Highways Authority of India (NHAI), despite a robust Rs 3.5 trillion pipeline. According to an HDFC Securities report, the shift to more cautious developer models now favours firms with strong balance sheets, as tighter qualification norms limit aggressive bidders.The revised norms mandate additional performance security, targeting the exclusion of players that previously submitted low bids—often 25 to 40 per cent below NHAI cost estimates—raisin..

Next Story
Infrastructure Transport

Mumbai Gets Coastal Nod for Next Promenade Phase

As Mumbai prepares to open two major sections of its expansive seafront promenade this week, the city’s civic authority has secured a key coastal clearance to advance further construction. The Maharashtra Coastal Zone Management Authority (MCZMA) has approved the commencement of work on the segment between Haji Ali and Baroda Palace, with tendering expected soon after project cost assessments.The promenade, stretching 7.5 km in length and 20 metres wide, is being designed as a flagship open space for walkers, joggers, and cyclists. Two critical stretches—2.75 km from Tata Garden to Haji Al..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?