IPSCDL Completes Final Surfacing of Central Panaji Roads
SMART CITIES

IPSCDL Completes Final Surfacing of Central Panaji Roads

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.

Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.

From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.

St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.

IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.

Source:Goemkarponn

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.Source:Goemkarponn

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code