IPSCDL Completes Final Surfacing of Central Panaji Roads
SMART CITIES

IPSCDL Completes Final Surfacing of Central Panaji Roads

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.

Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.

From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.

St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.

IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.

Source:Goemkarponn

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.Source:Goemkarponn

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->