IPSCDL Completes Final Surfacing of Central Panaji Roads
SMART CITIES

IPSCDL Completes Final Surfacing of Central Panaji Roads

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.

Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.

From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.

St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.

IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.

Source:Goemkarponn

Imagine Panaji Smart City Development Limited (IPSCDL) has completed the final layer of Bituminous Concrete surfacing for all three phases of the Central Panaji road redevelopment project, covering 6,850 metres. The project, executed under the Smart City Mission, included Dense Bituminous Macadam works and rectifications completed without major road closures.Phase one covered 735 metres, including MG Road and SV Road near Caculo Island and Don Bosco. Phase two added 1,024 metres across MG Road, TB Cunha Road, and 18 June Road. Phase three saw 1,415 metres completed from UCO Bank to Don Bosco, INOX, and nearby internal lanes.From April to May, the next phase includes traffic signage and road painting to improve safety and management. Landscaping is scheduled for June, using climate-resilient techniques to promote long-term ecological benefits.St. Inez Road, with 3,000 metres of concrete work, is nearing completion. The successful connection of the sewer line to the Sewage Treatment Plant has enabled final road work. Roads near Café Bhonsle Square have also reopened, easing traffic congestion.IPSCDL CEO Sanjit Rodrigues confirmed that the project remains on track, with focus now on sustainable delivery and urban resilience.Source:Goemkarponn

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App