Progress On Subansiri Lower Hydroelectric Project
POWER & RENEWABLE ENERGY

Progress On Subansiri Lower Hydroelectric Project

The Subansiri Lower Hydroelectric Project on the Subansiri River at the border of Arunachal Pradesh and Assam is being implemented by NHPC Limited and has an installed capacity of 2,000 megawatt (MW), comprising eight units of 250 megawatt each. Two units have been commissioned and the power generated is being supplied to the project beneficiaries. The remaining units are planned to be commissioned in a phased manner by December 2026.

Upon completion the project is expected to generate about 7,422 million units (mn units) of electricity annually and will contribute significantly to the country’s renewable energy generation. The project is expected to provide flood moderation benefits in the Brahmaputra Valley and to support grid stability by balancing intermittent solar and wind energy. It will also provide peaking power support to the national grid.

The Subansiri Lower Hydroelectric Project has obtained statutory environment and forest clearances from the concerned authorities and NHPC Limited has implemented riverbank protection and erosion control measures downstream of the project. Dam safety aspects are being ensured in accordance with the Dam Safety Act, 2021 under the guidance and recommendations of the National Dam Safety Authority. These measures are intended to maintain operational safety and environmental compliance.

NHPC Limited has taken initiatives to benefit local communities and stakeholders, providing employment to about 7,000 local workers during construction and implementing corporate social responsibility initiatives in education, skill development, health, sanitation and rural development. Livelihood programmes have benefited about 5,000 women and the project has contributed to the development of local infrastructure including roads and bridges, thereby improving connectivity for nearby villages. The information was provided by the Minister of State in the Ministry of Power, Shripad Naik, in a written reply in the Rajya Sabha today.

The Subansiri Lower Hydroelectric Project on the Subansiri River at the border of Arunachal Pradesh and Assam is being implemented by NHPC Limited and has an installed capacity of 2,000 megawatt (MW), comprising eight units of 250 megawatt each. Two units have been commissioned and the power generated is being supplied to the project beneficiaries. The remaining units are planned to be commissioned in a phased manner by December 2026. Upon completion the project is expected to generate about 7,422 million units (mn units) of electricity annually and will contribute significantly to the country’s renewable energy generation. The project is expected to provide flood moderation benefits in the Brahmaputra Valley and to support grid stability by balancing intermittent solar and wind energy. It will also provide peaking power support to the national grid. The Subansiri Lower Hydroelectric Project has obtained statutory environment and forest clearances from the concerned authorities and NHPC Limited has implemented riverbank protection and erosion control measures downstream of the project. Dam safety aspects are being ensured in accordance with the Dam Safety Act, 2021 under the guidance and recommendations of the National Dam Safety Authority. These measures are intended to maintain operational safety and environmental compliance. NHPC Limited has taken initiatives to benefit local communities and stakeholders, providing employment to about 7,000 local workers during construction and implementing corporate social responsibility initiatives in education, skill development, health, sanitation and rural development. Livelihood programmes have benefited about 5,000 women and the project has contributed to the development of local infrastructure including roads and bridges, thereby improving connectivity for nearby villages. The information was provided by the Minister of State in the Ministry of Power, Shripad Naik, in a written reply in the Rajya Sabha today.

Next Story
Infrastructure Urban

Narayanan G Appointed CEO of Athaang Infrastructure

Athaang Infrastructure Private Limited has appointed Mr Narayanan G as its Chief Executive Officer. He brings over 25 years of leadership experience in infrastructure investments, with more than $3 billion in capital deployment across roads, ports, logistics, energy and healthcare.Before joining Athaang, he served as Partner and Head – Transportation at IDFC Alternatives / Global Infrastructure Partners India. In this role, he contributed across the investment lifecycle, including fundraising, deal origination, portfolio management and successful exits.Mr Narayanan has also been involved in ..

Next Story
Equipment

Herrenknecht TBM Cleared for Mumbai Water Tunnel Project

Afcons Infrastructure, a Shapoorji Pallonji Group company, has cleared the factory acceptance tests for a Herrenknecht Gripper tunnel boring machine (TBM) with a diameter of 5.33 m. The machine will be deployed for the 7.2 km Bhiwandi–Thane water tunnel project connecting Kasheli to Mulund (Bhiwandi to Octroi Naka).The project is expected to strengthen Mumbai’s existing water transport network and help increase fresh water supply for millions of residents. Designed for hard rock excavation, the Gripper TBM is built for high performance, precision and reliability.The entire 7.2 km tunnel dr..

Next Story
Infrastructure Transport

Sector 51-52 Metro skywalk in Noida remains shut despite being ready for over a year

Thousands of commuters travelling between Delhi Metro Rail Corporation’s (DMRC) Sector 52 station and Noida Metro Rail Corporation’s (NMRC) Sector 51 station continue to face daily inconvenience as the 300-metre air-conditioned skywalk connecting the two stations remains closed, despite being completed over a year ago, according to a report.The Noida Metro Rail Corporation built the foot overbridge to enable a seamless interchange between the Delhi Metro and Noida Metro networks. However, pending finishing work and a structural obstruction have delayed its opening.Krishna Karunesh, Chief E..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement