Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline
ECONOMY & POLICY

Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge.

Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur.

The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished.

Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year.

Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge. Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur. The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished. Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year. Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

Next Story
Infrastructure Transport

Noida Airport Fuels NCR Realty Growth

The start of commercial operations at Noida International Airport has recently emerged as a major trigger for real estate growth across Noida, Greater Noida and the Yamuna Expressway region. The airport is expected to improve regional connectivity and support the next phase of development in eastern NCR.The airport, inaugurated on 28 March, has begun passenger services, while cargo operations are also expected to strengthen its role as an economic and logistics hub. Its operationalisation is expected to reduce dependence on Delhi’s Indira Gandhi International Airport for residents and busine..

Next Story
Technology

thyssenkrupp and GlobalLogic Form AI Alliance

thyssenkrupp AG and GlobalLogic, a Hitachi Group company, have recently formed a strategic alliance to deploy autonomous robotics and Physical AI across heavy industry operations. The partnership aims to improve safety, reduce engineering bottlenecks and accelerate industrial transformation at scale.The alliance brings together thyssenkrupp’s industrial expertise with Hitachi’s innovation capabilities. It includes GlobalLogic, Method and Hitachi America R&D, creating a “Lab-to-Scale” pipeline that connects research, digital strategy, design and enterprise software engineering for i..

Next Story
Real Estate

Platinum Corp Launches Luxury Suites in Santacruz

Platinum Corp has recently launched Platinum Stellar: Bespoke Presidential Suites, a premium residential project in Santacruz West, Mumbai. The development is positioned as a boutique luxury offering for homebuyers seeking expansive layouts, privacy and personalised living experiences.Located on Main Avenue, the project has been designed as a low-density, high-end residential address with spacious homes starting from 2,500 sq ft and extending to full-floor residences. The project targets HNIs, business owners and legacy residents from the Bandra-Khar-Santacruz belt.Platinum Stellar has been de..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement