Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline
ECONOMY & POLICY

Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge.

Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur.

The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished.

Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year.

Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge. Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur. The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished. Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year. Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->