Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline
ECONOMY & POLICY

Ajni Laxman Jhula First Phase Likely to Miss Pre-Monsoon Deadline

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge.

Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur.

The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished.

Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year.

Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

The Rs 3.32 billion (bn) Ajni Laxman Jhula six-lane twin cable-stayed bridge project has entered a stage in which the first phase is likely to miss its pre-monsoon completion target, with significant work still pending at the site. The structure is intended to replace the 125-year-old British-era Ajni railway overbridge. Maharashtra Rail Infrastructure Development Corporation (MRIDC), also known as MahaRail, is constructing one carriageway in the first phase, comprising three lanes to allow two-way traffic, while the second carriageway will be taken up after demolition of the existing bridge. Once fully completed, both carriageways will operate as one-way roadways to improve traffic flow between South and Central Nagpur. The project has experienced repeated delays owing to design modifications linked to parallel infrastructure projects, complexities of working directly above a busy railway line and prolonged statutory approval processes for the cable-stayed elements. MRIDC has completed two major abutments on either side of the railway, and work on the central pylon is underway, with the remaining pylon work estimated to require about one month. Precasting of slabs has been completed, and girders are being readied, but several key components remain unfinished. Construction began in April 2023, and the authority initially planned to open one side by October 2025, a schedule later moved to March 2026 and then to the pre-monsoon period; however, a recent site inspection indicated substantial residual work, making that target unlikely. MRIDC has not issued an official revised completion date, and sources indicate the first phase may now be finished only by the end of the year. Once operational the twin cable-stayed bridge is expected to reduce traffic congestion substantially and enhance connectivity across central Nagpur while also serving as an architectural landmark with LED theme lighting, footpaths on both sides and dedicated selfie points. Phased construction has avoided the need for traffic diversions and the design prepared by a Taiwan-based firm and approved by IIT Bombay has required multiple technical clearances that have contributed to the execution timeline.

Next Story
Resources

K2 Infragen appoints D K Raju to lead HAM projects

K2 Infragen has appointed D K Raju as Senior Vice President to lead its Hybrid Annuity Model (HAM) project portfolio, strengthening the company's execution capabilities as it expands its infrastructure business.Raju brings more than 27 years of experience in infrastructure project execution, planning, quantity surveying, tendering and technical operations. He has previously held senior positions at HG Infra Engineering, Allone Infra and Techno Unique Infratech.In his new role, Raju will oversee execution of K2 Infragen's Rs 3.91 billion Telangana road project under the Hybrid Annuity Model, in..

Next Story
Infrastructure Urban

AI Data Centre Leaders Map India’s Infrastructure Roadmap

Mumbai, 22 July 2026: As artificial intelligence reshapes global digital infrastructure, industry leaders gathered in Mumbai today at the AI-Powered Data Centre Conference 2026 to discuss how India can build the capacity, technology and ecosystem required to emerge as a global AI infrastructure hub. Organised by ASAPP Info Global Group and conceptualised by FIRST Construction Council, the conference revolved around the theme, “From Capacity Gap to AI Superpower: Building India's Digital Backbone for the Intelligence Economy.” Bringing together developers, technology providers, enterpr..

Next Story
Real Estate

SPML Infra raises over Rs 1.9 billion through preferential issue

SPML Infra has raised more than Rs 1.9 billion through a preferential issue of equity shares and convertible warrants, aimed at strengthening its balance sheet, funding growth and converting debt into equity.The company's board approved the allotment of 693,999 equity shares and 9.54 million convertible warrants at Rs 186 per security. The warrants are convertible into equity shares within 18 months in accordance with SEBI regulations.As part of the transaction, National Asset Reconstruction Company (NARCL) converted an existing loan of Rs 71.6 million into 384,858 equity shares. SPML said the..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement