No Blanket Extension Of ALMM List?II Beyond First Of June 2026
ECONOMY & POLICY

No Blanket Extension Of ALMM List?II Beyond First Of June 2026

The Ministry of New and Renewable Energy (MNRE) has decided that no blanket extension of the deadline for applicability of the Approved List of Models and Manufacturers List?II for solar photovoltaic (solar PV) cells beyond the first of June 2026 is necessary. The decision followed detailed examination of representations from stakeholders and consultations with the industry. Under the existing framework, net?metering and open access projects commissioned before the first of June 2026 are exempt from ALMM List?II, while projects commissioned after that date must comply.

To protect investments already made, MNRE said certain net?metering, open access and renewable energy power projects may be granted appropriate time extension on a case?to?case basis. Eligible cases include projects where module installation is complete but commissioning is pending, or where developers have taken effective steps such as land acquisition, financial closure, connectivity arrangements and approval of electrical drawings. Each claim will be assessed on the basis of supporting information and documentary proof.

Renewable power developers seeking extension beyond the first of June 2026 may submit claims with requisite documentary proof through a dedicated portal developed by the National Institute of Solar Energy (NISE) on or before the thirtieth of June 2026. Claims will be examined by an Expert Committee to be constituted by the Ministry, which will recommend project?wise relief based on the information provided. The Ministry said residential net?metering consumers who voluntarily forego government subsidy under the Give It Up campaign of the PM Surya Ghar: Muft Bijli Yojana will continue to be governed by existing scheme guidelines until the thirty?first of March 2027.

The decision noted consideration of the Office Memorandum dated the twenty?ninth of April 2026 which advised that the West Asia situation be treated as war and that time extension of not less than two months and not more than four months may be considered in specific cases. MNRE said the move aims to preserve policy stability and investor confidence and to support domestic solar PV manufacturing. Further details are available in O.M. No. 283/63/2025?GRID SOLAR dated the twenty?fifth of May 2026 on the official Ministry website.

The Ministry of New and Renewable Energy (MNRE) has decided that no blanket extension of the deadline for applicability of the Approved List of Models and Manufacturers List?II for solar photovoltaic (solar PV) cells beyond the first of June 2026 is necessary. The decision followed detailed examination of representations from stakeholders and consultations with the industry. Under the existing framework, net?metering and open access projects commissioned before the first of June 2026 are exempt from ALMM List?II, while projects commissioned after that date must comply. To protect investments already made, MNRE said certain net?metering, open access and renewable energy power projects may be granted appropriate time extension on a case?to?case basis. Eligible cases include projects where module installation is complete but commissioning is pending, or where developers have taken effective steps such as land acquisition, financial closure, connectivity arrangements and approval of electrical drawings. Each claim will be assessed on the basis of supporting information and documentary proof. Renewable power developers seeking extension beyond the first of June 2026 may submit claims with requisite documentary proof through a dedicated portal developed by the National Institute of Solar Energy (NISE) on or before the thirtieth of June 2026. Claims will be examined by an Expert Committee to be constituted by the Ministry, which will recommend project?wise relief based on the information provided. The Ministry said residential net?metering consumers who voluntarily forego government subsidy under the Give It Up campaign of the PM Surya Ghar: Muft Bijli Yojana will continue to be governed by existing scheme guidelines until the thirty?first of March 2027. The decision noted consideration of the Office Memorandum dated the twenty?ninth of April 2026 which advised that the West Asia situation be treated as war and that time extension of not less than two months and not more than four months may be considered in specific cases. MNRE said the move aims to preserve policy stability and investor confidence and to support domestic solar PV manufacturing. Further details are available in O.M. No. 283/63/2025?GRID SOLAR dated the twenty?fifth of May 2026 on the official Ministry website.

Next Story
Products

Fynd Launches AI Platform to Accelerate Fashion Creation

Fynd, an AI-native retail technology company backed by Reliance Retail Ventures, has launched Fynd Create, a platform designed to bring design intelligence, sourcing and manufacturing onto a single connected ecosystem. The platform aims to help brands respond faster to changing consumer preferences and shorten product development cycles.As social media trends continue to compress traditional fashion seasons, brands are under increasing pressure to move from seasonal planning to demand-driven production. Conventional supply chains, often characterised by long lead times and fragmented operation..

Next Story
Resources

Modis Navnirman Appointed For Neel Kiran CHSL Redevelopment

Modis Navnirman (MNL) has been appointed as the developer for the redevelopment of Neel Kiran Co-operative Housing Society Ltd in Khar West, Mumbai, following a selection process in which members chose MNL as their preferred partner. The appointment will add approximately Rs two point five billion (Rs two point five bn) to the company's Gross Development Value pipeline and strengthen its focus on redevelopment and urban renewal projects across the Mumbai Metropolitan Region. The project site is a landmark residential society in Khar West, and the selection reflects members' preference for a pa..

Next Story
Infrastructure Energy

Diamond Power Commissions Eighth MV and EHV Cable Line

Diamond Power Infrastructure (DPIL) has commissioned its eighth Medium Voltage (MV) and Extra High Voltage (EHV) power cable production line at its manufacturing facility in Vadodara, Gujarat. The new line enhances the company's manufacturing capacity in the technologically advanced MV and EHV underground power cable segment. This segment supplies cables for power transmission networks, power generation projects and renewable energy evacuation systems. The development is presented as a step to meet evolving infrastructure needs. The MV and EHV cables produced at the Vadodara facility serve urb..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement