Andheri Lokhandwala-Yari Road Bridge Project Delayed
ROADS & HIGHWAYS

Andheri Lokhandwala-Yari Road Bridge Project Delayed

The construction of the bridge connecting Lokhandwala to Yari Road in Andheri is unlikely to start before January due to pending no-objection certificates (NOCs) from the state forest department for the removal of 48 mangrove trees and the traffic police.

The forest department is conducting a panchnama to document the tree felling, and only after its completion will the NOC be issued. Additionally, 26 encroachments along the Lokhandwala side of the bridge need to be cleared.

Work delays were exacerbated by the recent assembly elections, but officials are hopeful that construction on the Yari Road side can commence once the NOCs are obtained. The bridge, expected to cost Rs 42 crore, aims to reduce travel time between Lokhandwala and Yari Road from 35 minutes to just five.

The construction of the bridge connecting Lokhandwala to Yari Road in Andheri is unlikely to start before January due to pending no-objection certificates (NOCs) from the state forest department for the removal of 48 mangrove trees and the traffic police. The forest department is conducting a panchnama to document the tree felling, and only after its completion will the NOC be issued. Additionally, 26 encroachments along the Lokhandwala side of the bridge need to be cleared. Work delays were exacerbated by the recent assembly elections, but officials are hopeful that construction on the Yari Road side can commence once the NOCs are obtained. The bridge, expected to cost Rs 42 crore, aims to reduce travel time between Lokhandwala and Yari Road from 35 minutes to just five.

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?