RRR North Works To Begin In August Operational By End Of 2029
ROADS & HIGHWAYS

RRR North Works To Begin In August Operational By End Of 2029

The National Highways Authority of India has issued tenders for the northern segment of the Hyderabad Regional Ring Road, a 161-km six-lane access-controlled greenfield expressway. Bids must be submitted online by July seven and technical bids will be opened on July eight. The authority said works are likely to commence in August and the corridor is expected to become operational by the end of 2029 to enhance regional connectivity around Hyderabad.

Procurement will follow Design, Build, Operate and Transfer or Hybrid Annuity Model routes, and contractors will have three years from the date of issue of the Letter of Agreement to complete the works. The NHAI has reconfigured the scheme into two packages instead of five and assigned the highway the number NH-161AA to streamline bidding and delivery.

The corridor will include 44 major bridges, 127 minor bridges, four road-over-bridges, 44 underpasses, 1,262 culverts and nine toll plazas, and will link with National Highways and State Highways at nine points. The 161.518-km stretch from Girmapur in Sangareddy district to Tangadpally in Yadadri Bhuvanagiri district has been estimated at an overall civil construction cost of Rs 93.624 billion (Rs 93.624 bn). Package one covers 83.518 km at an estimated Rs 49.187 bn and Package two covers 78 km at an estimated Rs 44.43 bn.

The northern segment experienced repeated delays, including an earlier attempt when the project was divided into five packages and received no bids after documentation was not uploaded during tendering. The NHAI reduced the number of packages to two in February 2026 and has reported rapid progress on land acquisition, with 927 hectares secured for Package one and 886 hectares for Package two. Awards have been announced for more than 70 per cent of the acquired land while remaining cases progress.

The National Highways Authority of India has issued tenders for the northern segment of the Hyderabad Regional Ring Road, a 161-km six-lane access-controlled greenfield expressway. Bids must be submitted online by July seven and technical bids will be opened on July eight. The authority said works are likely to commence in August and the corridor is expected to become operational by the end of 2029 to enhance regional connectivity around Hyderabad. Procurement will follow Design, Build, Operate and Transfer or Hybrid Annuity Model routes, and contractors will have three years from the date of issue of the Letter of Agreement to complete the works. The NHAI has reconfigured the scheme into two packages instead of five and assigned the highway the number NH-161AA to streamline bidding and delivery. The corridor will include 44 major bridges, 127 minor bridges, four road-over-bridges, 44 underpasses, 1,262 culverts and nine toll plazas, and will link with National Highways and State Highways at nine points. The 161.518-km stretch from Girmapur in Sangareddy district to Tangadpally in Yadadri Bhuvanagiri district has been estimated at an overall civil construction cost of Rs 93.624 billion (Rs 93.624 bn). Package one covers 83.518 km at an estimated Rs 49.187 bn and Package two covers 78 km at an estimated Rs 44.43 bn. The northern segment experienced repeated delays, including an earlier attempt when the project was divided into five packages and received no bids after documentation was not uploaded during tendering. The NHAI reduced the number of packages to two in February 2026 and has reported rapid progress on land acquisition, with 927 hectares secured for Package one and 886 hectares for Package two. Awards have been announced for more than 70 per cent of the acquired land while remaining cases progress.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->