Kanpur Metro Completes Third Rail Works on Key Elevated Stretch
RAILWAYS & METRO RAIL

Kanpur Metro Completes Third Rail Works on Key Elevated Stretch

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta.

This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule.

Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out.

The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness.

Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily.

The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta. This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule. Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out. The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness. Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily. The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement