Kanpur Metro Completes Third Rail Works on Key Elevated Stretch
RAILWAYS & METRO RAIL

Kanpur Metro Completes Third Rail Works on Key Elevated Stretch

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta.

This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule.

Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out.

The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness.

Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily.

The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta. This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule. Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out. The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness. Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily. The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement