Kanpur Metro Completes Third Rail Works on Key Elevated Stretch
RAILWAYS & METRO RAIL

Kanpur Metro Completes Third Rail Works on Key Elevated Stretch

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta.

This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule.

Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out.

The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness.

Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily.

The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta. This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule. Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out. The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness. Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily. The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

Next Story
Infrastructure Urban

Implementation Status of Jal Jeevan Mission

Since August 2019 the Government has implemented Jal Jeevan Mission to provide assured potable water through household tap connections in rural India. At the start of the mission only 32.3 million (mn) rural households, representing 16.7 per cent, were reported to have tap water connections. States and union territories have reported that 125.8 mn additional rural households have since been provided with tap connections. As a result, of about 193.6 mn rural households roughly 158.2 mn, or 81.71 per cent, are reported to have tap water supply at home.\n\nThe State, district and village level st..

Next Story
Infrastructure Urban

Jal Jeevan Mission Reaches Eighty One Per Cent Rural Coverage

The Government reported substantial progress under the Jal Jeevan Mission, launched in August 2019 to provide tap water to every rural household. At launch only 32.3 million (mn) rural households had tap connections and states and Union territories reported provision of 125.8 mn additional households by March 2026. Consequently, out of about 193.6 mn rural households around 158.2 mn, or 81.71 per cent, are reported to have tap water at home. The Finance Minister announced extension of the mission until 2028 in the 2025-26 budget speech. The Swachh Bharat Mission Grameen, launched in October 20..

Next Story
Infrastructure Urban

Empowering Local Governance for Sustainable Rural Water Supply

The Ministry of Jal Shakti has aligned the Jal Jeevan Mission (JJM) with the 73rd Amendment to strengthen village level planning and community ownership of water supply. Gram Panchayats, village water and sanitation committees and Pani Samitis are to plan, implement, manage and maintain piped water systems, with gram sabha processes formalising handover and oversight. Implementation support agencies including non government organisations, community based organisations and self help groups have been empanelled to train local committees and promote women participation. Under JJM, the department ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement