Kanpur Metro Completes Third Rail Works on Key Elevated Stretch
RAILWAYS & METRO RAIL

Kanpur Metro Completes Third Rail Works on Key Elevated Stretch

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta.

This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule.

Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out.

The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness.

Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily.

The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

The Kanpur Metro project has achieved a key construction milestone with the successful installation of the Third Rail power system on the 5.3 km-long Baradevi–Naubasta elevated section of Corridor 1, which runs from IIT Kanpur to Naubasta. This stretch forms part of the remaining balance section between Kanpur Central and Naubasta. Trains on the Kanpur Metro network operate using a 750-volt DC Third Rail system, and the installation was carried out alongside track laying to avoid delays to the overall project schedule. Track construction on the elevated section was completed by the end of October 2025, following which Third Rail installation works were taken up and have now been fully completed. In addition to the physical installation, all mandatory safety checks, technical tests and inspection procedures related to the power system have been successfully carried out. The section has also received the necessary approvals from the Electrical Inspector General, clearing an important regulatory requirement ahead of further trial runs and operational readiness. Providing an update on other parts of the project, Sushil Kumar, managing director of Uttar Pradesh Metro Rail Corporation Limited, said that track construction in the underground section between Kanpur Central and the Swadeshi Cotton Mill ramp is progressing at a rapid pace. He added that construction work on Corridors 1 and 2 is expected to continue steadily. The completion of Third Rail works on the Baradevi–Naubasta stretch marks another step forward in expanding Kanpur’s metro network and improving urban mobility in the city.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code