Kanpur Metro Tunnelling Completed as TBM Parvati Breaks Through
RAILWAYS & METRO RAIL

Kanpur Metro Tunnelling Completed as TBM Parvati Breaks Through

Tunnel Boring Machine (TBM) Parvati has completed its breakthrough at Double Pulia station, marking the completion of tunnelling work on the Kanpur Metro project. Project authorities reported that the machine reached the designated station after final drive operations were completed and the tunnelling phase of the underground section was declared finished. The breakthrough caps a sustained engineering effort that combined mechanised excavation with continuous monitoring to manage ground conditions beneath the city.

Following the breakthrough, preparatory activities have begun to ready the tunnel for track installation and systems integration. Engineers will undertake lining completion, grouting and inspections to ensure structural stability and alignment ahead of rails and signalling works. Utility relocations and station fit out are expected to proceed in sequence so that mechanical, electrical and communications systems can be integrated without undue delay.

Project managers indicated that the tunnelling campaign relied on detailed geotechnical studies and real time monitoring to mitigate settlement and protect surface structures. The TBM was adapted to local ground conditions and operated with support systems for muck removal and segment erection, enabling a continuous advance through variable strata. Safety protocols and community liaison were maintained throughout the drives to minimise disruption and coordinate access around work sites.

With tunnelling now complete, attention will shift to completing stations and testing systems ahead of commissioning. The milestone is expected to accelerate subsequent phases of construction and to support planned service delivery once integration and safety verification are finished. Stakeholders said coordination will continue to maintain schedules and to address any residual technical issues.

Tunnel Boring Machine (TBM) Parvati has completed its breakthrough at Double Pulia station, marking the completion of tunnelling work on the Kanpur Metro project. Project authorities reported that the machine reached the designated station after final drive operations were completed and the tunnelling phase of the underground section was declared finished. The breakthrough caps a sustained engineering effort that combined mechanised excavation with continuous monitoring to manage ground conditions beneath the city. Following the breakthrough, preparatory activities have begun to ready the tunnel for track installation and systems integration. Engineers will undertake lining completion, grouting and inspections to ensure structural stability and alignment ahead of rails and signalling works. Utility relocations and station fit out are expected to proceed in sequence so that mechanical, electrical and communications systems can be integrated without undue delay. Project managers indicated that the tunnelling campaign relied on detailed geotechnical studies and real time monitoring to mitigate settlement and protect surface structures. The TBM was adapted to local ground conditions and operated with support systems for muck removal and segment erection, enabling a continuous advance through variable strata. Safety protocols and community liaison were maintained throughout the drives to minimise disruption and coordinate access around work sites. With tunnelling now complete, attention will shift to completing stations and testing systems ahead of commissioning. The milestone is expected to accelerate subsequent phases of construction and to support planned service delivery once integration and safety verification are finished. Stakeholders said coordination will continue to maintain schedules and to address any residual technical issues.

Next Story
Infrastructure Energy

India Adds Record 44.61 GW Solar Capacity in FY2026

India’s solar sector reached a milestone in FY2026, with cumulative installed capacity crossing 150 GW and annual additions hitting a record 44.61 GW, exceeding the government target of 34 GW and nearly doubling FY2025’s 23.83 GW. Distributed Renewable Energy contributed 16.3 GW, while PPA and C&I segments accounted for 34 per cent and 30 per cent, respectively.India has risen from 9th globally in 2015 to 3rd in cumulative solar capacity by 2025 and is set to become the world’s second-largest solar market in annual installations in 2026. Seven states, led by Rajasthan and Gujarat, ac..

Next Story
Real Estate

Abhee Ventures unveils Scottish-themed 45-acre township in Bengaluru

Abhee Ventures, a leading South Indian real estate developer, has announced “Codename New Dimension,” a 45-acre Scottish-themed residential township at Gunjur on Whitefield–Sarjapur Road, Bengaluru. Strategically located between Whitefield and Sarjapur Road, Gunjur benefits from strong connectivity to the Outer Ring Road IT corridor, ITPL, EPIP, the upcoming Dommasandra Metro Station, and the proposed SWIFT City and Peripheral Ring Road.The township, designed in collaboration with London-based UHA London and India’s RSP Architects, offers low-density living with 85 per cent open spaces..

Next Story
Infrastructure Urban

Hindalco unveils Eternia experience centre for high-performance aluminium windows

Hindalco Industries, the metals flagship of the Aditya Birla Group, has launched its Eternia experience centre in Lajpat Nagar, New Delhi, highlighting its high-performance aluminium window systems designed for India’s evolving construction sector. The company is also expanding its manufacturing footprint in North India with a new Bilaspur facility.Eternia has emerged as one of the fastest-growing brands in system aluminium windows, registering nearly 65 per cent CAGR over the last three years. With a nationwide network of 170+ channel partners across 100+ cities, the brand serves homeowners..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement