CERC Introduces Graded Compensation For Renewable Connectivity Delays
POWER & RENEWABLE ENERGY

CERC Introduces Graded Compensation For Renewable Connectivity Delays

The Central Electricity Regulatory Commission (CERC) has introduced a graded compensation framework for delays in meeting renewable project connectivity milestones, aiming to free scarce transmission capacity and encourage timely implementation. The procedure allows eligible developers to seek additional time subject to payment of charges and specified eligibility conditions rather than automatic extensions. The Commission indicated the mechanism is optional and intended to balance flexibility for projects showing progress with measures to prevent indefinite reservation of connectivity.

For requests to submit land documentation an applicant must have land documents covering at least 20 per cent of the land required for the connectivity capacity and submit these at least 15 working days before the original compliance deadline. The same 20 per cent threshold applies to applications for extension for financial closure. For extensions to achieve the commercial operation date (CoD) entities following the land or land-BG route must demonstrate documents for at least 75 per cent of required land while those under the LOA/PPA route must demonstrate 50 per cent.

The Central Transmission Utility of India (CTUIL) will scrutinise submitted documents and applicants will be allowed to rectify deficiencies within prescribed timelines. Developers must also provide details of contracts for major equipment and civil and electrical works. Failure to meet timelines or to pay applicable charges will result in closure of the application for additional time and connectivity will be dealt with under the existing GNA provisions.

Compensation is structured through milestone extension charges (MEC). For land and financial closure milestones the base charge has been fixed at Rs 1,000 per megawatt (MW) per day while the base charge for additional time to achieve CoD is Rs 3,000 per MW per day. For land compliance the Rs 1,000 per MW per day rate applies during the first month, rises by 10 per cent to Rs 1,100 in the second month and to Rs 1,200 in the third month, with a maximum additional period of three months.

For financial closure the Rs 1,000 per MW per day rate applies for the first three months, rising to Rs 1,100 in the fourth month, Rs 1,200 in the fifth month and Rs 1,300 in the sixth month, with a maximum extension of six months. Delays in achieving CoD attract steeper charges: Rs 3,000 per MW per day for the first six months, increases of 10 per cent each month in months seven to nine reaching Rs 3,900 in the ninth month, and Rs 6,000 per MW per day in months 10 to 12, with a maximum extension of 12 months. MEC are payable in advance, generally 15 days before the period, and failure to pay can lead to revocation of connectivity while early completion can trigger a refund of unused charges without interest. The Commission rejected calls for exemptions where delays arose from factors beyond developer control, reiterated that the mechanism will not override power purchase agreements or dilute liquidated damages provisions, and said the procedure applies to all eligible entities from the date of the order after consultation with 42 stakeholders and a public hearing on 19 May 2026.

The Central Electricity Regulatory Commission (CERC) has introduced a graded compensation framework for delays in meeting renewable project connectivity milestones, aiming to free scarce transmission capacity and encourage timely implementation. The procedure allows eligible developers to seek additional time subject to payment of charges and specified eligibility conditions rather than automatic extensions. The Commission indicated the mechanism is optional and intended to balance flexibility for projects showing progress with measures to prevent indefinite reservation of connectivity. For requests to submit land documentation an applicant must have land documents covering at least 20 per cent of the land required for the connectivity capacity and submit these at least 15 working days before the original compliance deadline. The same 20 per cent threshold applies to applications for extension for financial closure. For extensions to achieve the commercial operation date (CoD) entities following the land or land-BG route must demonstrate documents for at least 75 per cent of required land while those under the LOA/PPA route must demonstrate 50 per cent. The Central Transmission Utility of India (CTUIL) will scrutinise submitted documents and applicants will be allowed to rectify deficiencies within prescribed timelines. Developers must also provide details of contracts for major equipment and civil and electrical works. Failure to meet timelines or to pay applicable charges will result in closure of the application for additional time and connectivity will be dealt with under the existing GNA provisions. Compensation is structured through milestone extension charges (MEC). For land and financial closure milestones the base charge has been fixed at Rs 1,000 per megawatt (MW) per day while the base charge for additional time to achieve CoD is Rs 3,000 per MW per day. For land compliance the Rs 1,000 per MW per day rate applies during the first month, rises by 10 per cent to Rs 1,100 in the second month and to Rs 1,200 in the third month, with a maximum additional period of three months. For financial closure the Rs 1,000 per MW per day rate applies for the first three months, rising to Rs 1,100 in the fourth month, Rs 1,200 in the fifth month and Rs 1,300 in the sixth month, with a maximum extension of six months. Delays in achieving CoD attract steeper charges: Rs 3,000 per MW per day for the first six months, increases of 10 per cent each month in months seven to nine reaching Rs 3,900 in the ninth month, and Rs 6,000 per MW per day in months 10 to 12, with a maximum extension of 12 months. MEC are payable in advance, generally 15 days before the period, and failure to pay can lead to revocation of connectivity while early completion can trigger a refund of unused charges without interest. The Commission rejected calls for exemptions where delays arose from factors beyond developer control, reiterated that the mechanism will not override power purchase agreements or dilute liquidated damages provisions, and said the procedure applies to all eligible entities from the date of the order after consultation with 42 stakeholders and a public hearing on 19 May 2026.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code