+
CERC Introduces Graded Compensation For Renewable Connectivity Delays
POWER & RENEWABLE ENERGY

CERC Introduces Graded Compensation For Renewable Connectivity Delays

The Central Electricity Regulatory Commission (CERC) has introduced a graded compensation framework for delays in meeting renewable project connectivity milestones, aiming to free scarce transmission capacity and encourage timely implementation. The procedure allows eligible developers to seek additional time subject to payment of charges and specified eligibility conditions rather than automatic extensions. The Commission indicated the mechanism is optional and intended to balance flexibility for projects showing progress with measures to prevent indefinite reservation of connectivity.

For requests to submit land documentation an applicant must have land documents covering at least 20 per cent of the land required for the connectivity capacity and submit these at least 15 working days before the original compliance deadline. The same 20 per cent threshold applies to applications for extension for financial closure. For extensions to achieve the commercial operation date (CoD) entities following the land or land-BG route must demonstrate documents for at least 75 per cent of required land while those under the LOA/PPA route must demonstrate 50 per cent.

The Central Transmission Utility of India (CTUIL) will scrutinise submitted documents and applicants will be allowed to rectify deficiencies within prescribed timelines. Developers must also provide details of contracts for major equipment and civil and electrical works. Failure to meet timelines or to pay applicable charges will result in closure of the application for additional time and connectivity will be dealt with under the existing GNA provisions.

Compensation is structured through milestone extension charges (MEC). For land and financial closure milestones the base charge has been fixed at Rs 1,000 per megawatt (MW) per day while the base charge for additional time to achieve CoD is Rs 3,000 per MW per day. For land compliance the Rs 1,000 per MW per day rate applies during the first month, rises by 10 per cent to Rs 1,100 in the second month and to Rs 1,200 in the third month, with a maximum additional period of three months.

For financial closure the Rs 1,000 per MW per day rate applies for the first three months, rising to Rs 1,100 in the fourth month, Rs 1,200 in the fifth month and Rs 1,300 in the sixth month, with a maximum extension of six months. Delays in achieving CoD attract steeper charges: Rs 3,000 per MW per day for the first six months, increases of 10 per cent each month in months seven to nine reaching Rs 3,900 in the ninth month, and Rs 6,000 per MW per day in months 10 to 12, with a maximum extension of 12 months. MEC are payable in advance, generally 15 days before the period, and failure to pay can lead to revocation of connectivity while early completion can trigger a refund of unused charges without interest. The Commission rejected calls for exemptions where delays arose from factors beyond developer control, reiterated that the mechanism will not override power purchase agreements or dilute liquidated damages provisions, and said the procedure applies to all eligible entities from the date of the order after consultation with 42 stakeholders and a public hearing on 19 May 2026.

The Central Electricity Regulatory Commission (CERC) has introduced a graded compensation framework for delays in meeting renewable project connectivity milestones, aiming to free scarce transmission capacity and encourage timely implementation. The procedure allows eligible developers to seek additional time subject to payment of charges and specified eligibility conditions rather than automatic extensions. The Commission indicated the mechanism is optional and intended to balance flexibility for projects showing progress with measures to prevent indefinite reservation of connectivity. For requests to submit land documentation an applicant must have land documents covering at least 20 per cent of the land required for the connectivity capacity and submit these at least 15 working days before the original compliance deadline. The same 20 per cent threshold applies to applications for extension for financial closure. For extensions to achieve the commercial operation date (CoD) entities following the land or land-BG route must demonstrate documents for at least 75 per cent of required land while those under the LOA/PPA route must demonstrate 50 per cent. The Central Transmission Utility of India (CTUIL) will scrutinise submitted documents and applicants will be allowed to rectify deficiencies within prescribed timelines. Developers must also provide details of contracts for major equipment and civil and electrical works. Failure to meet timelines or to pay applicable charges will result in closure of the application for additional time and connectivity will be dealt with under the existing GNA provisions. Compensation is structured through milestone extension charges (MEC). For land and financial closure milestones the base charge has been fixed at Rs 1,000 per megawatt (MW) per day while the base charge for additional time to achieve CoD is Rs 3,000 per MW per day. For land compliance the Rs 1,000 per MW per day rate applies during the first month, rises by 10 per cent to Rs 1,100 in the second month and to Rs 1,200 in the third month, with a maximum additional period of three months. For financial closure the Rs 1,000 per MW per day rate applies for the first three months, rising to Rs 1,100 in the fourth month, Rs 1,200 in the fifth month and Rs 1,300 in the sixth month, with a maximum extension of six months. Delays in achieving CoD attract steeper charges: Rs 3,000 per MW per day for the first six months, increases of 10 per cent each month in months seven to nine reaching Rs 3,900 in the ninth month, and Rs 6,000 per MW per day in months 10 to 12, with a maximum extension of 12 months. MEC are payable in advance, generally 15 days before the period, and failure to pay can lead to revocation of connectivity while early completion can trigger a refund of unused charges without interest. The Commission rejected calls for exemptions where delays arose from factors beyond developer control, reiterated that the mechanism will not override power purchase agreements or dilute liquidated damages provisions, and said the procedure applies to all eligible entities from the date of the order after consultation with 42 stakeholders and a public hearing on 19 May 2026.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Madhya Pradesh Plans Airport Every 150 Km, Airstrip Every 75 Km

The Madhya Pradesh government plans to establish an airport every 150 km, an airstrip every 75 km and a helipad every 45 km, according to the state aviation department. Airports being developed in Ujjain and Shivpuri are expected to take the state’s airport count to 10. The government stated that Madhya Pradesh currently has eight airports in eight cities. The locations named by the department include Indore, Bhopal, Jabalpur, Gwalior, Khajuraho, Rewa and Satna. The state also has more than 20 airstrips and 220 helipads, while permanent helipads are planned in all 230 Assembly constituencies..

Next Story
Infrastructure Transport

West Bengal Plans Four Airports for 2028 Completion Under UDAN

West Bengal will develop four new airports under an agreement signed between the Union Civil Aviation Ministry and the state government, with all facilities targeted for completion by 2028. Union Civil Aviation Minister K Rammohan Naidu said the airports would be located at Charra in Purulia, Kalaikunda in Paschim Medinipur, Balurghat in Dakshin Dinajpur and Hasimara in Alipurduar. The project is part of the Centre’s regional connectivity UDAN programme. The Union government has committed Rs. 290 bn for West Bengal’s aviation sector over the next decade, while the state government will pro..

Next Story
Infrastructure Transport

Mumbai Airport Bars Russian Airlines as Agent Seeks Ministry Intervention

Mumbai airport has stopped accepting cargo booked on Russian flag carrier Aeroflot, disrupting shipments and prompting the airline’s cargo sales agent, Delmos Aviation, to seek intervention from the Ministry of Civil Aviation. The restrictions also affect cargo booked on Volga-Dnepr Airlines, according to a letter submitted by Delmos Aviation to the ministry on September 30. Aeroflot operates daily flights between Moscow and Delhi and runs a winter seasonal service to Goa. Bonded cargo from Mumbai and other cities is transported by road to Delhi before being flown to Russia. The agent said t..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code