Karnataka infrastructure minister reviews railway projects
RAILWAYS & METRO RAIL

Karnataka infrastructure minister reviews railway projects

Karnataka's Infrastructure Development Minister M B Patil convened a crucial review meeting with South Western Railway officials to assess the progress of several railway projects being undertaken with cost-sharing from the central government.

The meeting addressed various challenges, including land acquisition issues impacting key projects such as Gadag-Wadi, Dharwad-Belagavi, Tumkuru-Davanagere, and Tumkuru-Rayadurga. The aim was to identify and implement actions to accelerate these projects.

According to a statement from the minister's office, Patil engaged with several officials by phone, including Ministers Priyank Kharge, Lakshmi Hebbalkar, Santosh Lad, and the Deputy Commissioners of Davanagere and Haveri districts, as well as senior representatives from Krishna Jala Bhagya Nigam. He urged them to address project-specific issues within their districts and announced plans to meet soon with Union Minister of State for Railways V Somanna.

The review also covered the 242 km double track between Gadag-Hotgi, the 45 km double track between Bagalkote and Kudachi, challenges related to small bridges in the Almatti backwater region, delays in initiating the Vande Bharat train to Vijayapura, and infrastructure issues at Hubballi South Railway Station.

Patil highlighted that resolving these issues could potentially reduce travel time from Bengaluru to Vijayapura to approximately 10 hours. Currently, trains from Bengaluru to North Karnataka divert via Gadag, bypassing Gadag Main Station before continuing towards Vijayapura and Solapur. Improving Hubballi Station to facilitate direct routes and avoid engine changes could further streamline travel between Bengaluru and Vijayapura. The review also focused on the Gadag-Wadi, Bagalkote-Kudachi, Tumkuru-Davanagere, and Tumkuru-Rayadurga projects. (ET)

Karnataka's Infrastructure Development Minister M B Patil convened a crucial review meeting with South Western Railway officials to assess the progress of several railway projects being undertaken with cost-sharing from the central government. The meeting addressed various challenges, including land acquisition issues impacting key projects such as Gadag-Wadi, Dharwad-Belagavi, Tumkuru-Davanagere, and Tumkuru-Rayadurga. The aim was to identify and implement actions to accelerate these projects. According to a statement from the minister's office, Patil engaged with several officials by phone, including Ministers Priyank Kharge, Lakshmi Hebbalkar, Santosh Lad, and the Deputy Commissioners of Davanagere and Haveri districts, as well as senior representatives from Krishna Jala Bhagya Nigam. He urged them to address project-specific issues within their districts and announced plans to meet soon with Union Minister of State for Railways V Somanna. The review also covered the 242 km double track between Gadag-Hotgi, the 45 km double track between Bagalkote and Kudachi, challenges related to small bridges in the Almatti backwater region, delays in initiating the Vande Bharat train to Vijayapura, and infrastructure issues at Hubballi South Railway Station. Patil highlighted that resolving these issues could potentially reduce travel time from Bengaluru to Vijayapura to approximately 10 hours. Currently, trains from Bengaluru to North Karnataka divert via Gadag, bypassing Gadag Main Station before continuing towards Vijayapura and Solapur. Improving Hubballi Station to facilitate direct routes and avoid engine changes could further streamline travel between Bengaluru and Vijayapura. The review also focused on the Gadag-Wadi, Bagalkote-Kudachi, Tumkuru-Davanagere, and Tumkuru-Rayadurga projects. (ET)

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement