Secunderabad Station Redevelopment Moves Ahead Swiftly
RAILWAYS & METRO RAIL

Secunderabad Station Redevelopment Moves Ahead Swiftly

Redevelopment of Secunderabad railway station is progressing rapidly, with the new Railway Protection Force (RPF) building already completed. Construction is actively underway on several key components, including the air concourse, multi-level car parking (MLCP), foot over bridges (FOBs), elevators, the north-side main building, and an electric sub-station on the south side.

The RPF building, along with a temporary booking office, is among the early completed elements of the project. Work is advancing steadily on the basement construction on the southern side, foundation work, and the new foot over bridge at the Kazipet end.
According to South Central Railway (SCR) officials, most of the foundation work on the south side is complete. The redevelopment project, awarded to Girdharilal Construction Private Limited, is valued at approximately Rs 7.2 billion, with a scheduled completion by late 2025 or early 2026.

Two upgraded 33 KV electrical substations will replace the earlier 11 KV units to meet the station’s increased power requirements. A six-floor MLCP is being built on the northern side, with over 50 per cent of the foundation and structural work already finished.

SCR authorities emphasised that the redevelopment is being carried out with minimal disruption to passengers. The revamped station will feature modern architectural design and world-class passenger amenities. Officials added that the construction is being closely monitored to ensure strict adherence to safety standards.

Secunderabad Redevelopment Progress Overview:
  • RPF Building: Fully completed
  • South Side: Basement 90 per cent complete, to include parking for 200 vehicles and drop-off zone on ground floor
  • North Side: Construction of six-floor MLCP in progress
  • Kazipet End FOB: Foundation work completed

Redevelopment of Secunderabad railway station is progressing rapidly, with the new Railway Protection Force (RPF) building already completed. Construction is actively underway on several key components, including the air concourse, multi-level car parking (MLCP), foot over bridges (FOBs), elevators, the north-side main building, and an electric sub-station on the south side.The RPF building, along with a temporary booking office, is among the early completed elements of the project. Work is advancing steadily on the basement construction on the southern side, foundation work, and the new foot over bridge at the Kazipet end.According to South Central Railway (SCR) officials, most of the foundation work on the south side is complete. The redevelopment project, awarded to Girdharilal Construction Private Limited, is valued at approximately Rs 7.2 billion, with a scheduled completion by late 2025 or early 2026.Two upgraded 33 KV electrical substations will replace the earlier 11 KV units to meet the station’s increased power requirements. A six-floor MLCP is being built on the northern side, with over 50 per cent of the foundation and structural work already finished.SCR authorities emphasised that the redevelopment is being carried out with minimal disruption to passengers. The revamped station will feature modern architectural design and world-class passenger amenities. Officials added that the construction is being closely monitored to ensure strict adherence to safety standards.Secunderabad Redevelopment Progress Overview:RPF Building: Fully completedSouth Side: Basement 90 per cent complete, to include parking for 200 vehicles and drop-off zone on ground floorNorth Side: Construction of six-floor MLCP in progressKazipet End FOB: Foundation work completed

Next Story
Real Estate

CREDAI-MCHI to Host 10th Design & Construction Conference

CREDAI-MCHI will host the 10th anniversary edition of its Design & Construction Conference on August 19, 2026, at the Jio World Convention Centre in Mumbai.The event is expected to bring together more than 500 procurement leaders, construction heads, architects, consultants and senior real estate decision-makers, alongside over 50 construction and ancillary brands.The conference will feature product launches, technology showcases, knowledge sessions, strategic business-to-business networking and recognition of procurement professionals contributing to the transformation of the construction..

Next Story
Infrastructure Energy

BorgWarner Wins Extension for High-Voltage Inverter Programmes

BorgWarner has secured a major extension of several high-volume high-voltage inverter programmes from a leading European automotive manufacturer.The contracts cover updated inverter designs for plug-in hybrid and 800V battery-electric vehicle applications. Production is scheduled to begin in 2029.Isabelle McKenzie, President and General Manager, BorgWarner PowerDrive Systems, said the programme extensions demonstrate the company’s position in power electronics and reflect the strength of its technology, in-house expertise and customer relationships.For plug-in hybrid vehicles, BorgWarner wil..

Next Story
Infrastructure Urban

Castrol India Q2 Profit Rises 43% to Rs 3.48 bn

Castrol India reported a 43 per cent year-on-year increase in profit after tax to Rs 3.48 billion for the quarter ended June 30, 2026, supported by growth across its consumer, industrial and institutional businesses.Revenue from operations increased 25 per cent to Rs 18.71 billion during the second quarter of 2026, compared with Rs 14.97 billion in the corresponding period of 2025. EBITDA rose 41 per cent to Rs 4.94 billion from Rs 3.50 billion.Sequentially, revenue increased from Rs 15.45 billion in the first quarter of 2026, while EBITDA rose from Rs 3.29 billion. Profit after tax increased ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement