90% of sewerage, infra work done in Smart City
SMART CITIES

90% of sewerage, infra work done in Smart City

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised.

In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish.

Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress.

Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised. In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish. Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress. Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?