90% of sewerage, infra work done in Smart City
SMART CITIES

90% of sewerage, infra work done in Smart City

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised.

In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish.

Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress.

Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised. In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish. Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress. Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->