90% of sewerage, infra work done in Smart City
SMART CITIES

90% of sewerage, infra work done in Smart City

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised.

In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish.

Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress.

Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised. In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish. Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress. Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Next Story
Infrastructure Urban

Centre Disburses Over Rs 24,610 mn in XV Finance Commission Grants

The Union Government has released XV Finance Commission tied grants during the financial year 2025–26 to rural local bodies in Chhattisgarh, Gujarat, Madhya Pradesh, Punjab and Sikkim and has released withheld portions of tied and untied grants to Himachal Pradesh, Odisha and Tripura. The total disbursal exceeded Rs 24,610 mn, with figures expressed in million (mn) thereafter. The releases cover allocations pertaining to different financial years and aim to strengthen rural local governance. State-wise disbursements included Rs 3,324.6 mn for Punjab, Rs 9,432.7 mn for Madhya Pradesh, Rs 3,47..

Next Story
Infrastructure Urban

Centre Releases Over Rs 15 bn as XV FC Grants to Rural Bodies

The Union Government has released over Rs 15 bn in grants recommended by the Fifteenth Finance Commission (XV FC) to strengthen Panchayati Raj Institutions (PRIs) and Rural Local Bodies (RLBs) in six states. The funds comprise tied and untied grants disbursed in FY 2025–26. Telangana received Rs 2.48 bn as the first instalment of untied grants for FY 2025–26, benefitting 12600 Gram Panchayats (GPs). Uttarakhand received Rs 913.1 mn as the second instalment and an additional Rs 18.4 mn of a withheld first instalment was released to a further 216 GPs. Mizoram is included among beneficiary st..

Next Story
Infrastructure Energy

Government Assures Fuel Supplies And Seafarer Safety Amid West Asia Developments

The Government of India has stepped up coordinated measures to maintain stability in critical sectors as developments in West Asia continue to unfold. It has prioritised uninterrupted energy supplies, safeguarded maritime operations and extended consular assistance to nationals. Central authorities are working with State and Union territory administrations to ensure timely information dissemination and operational continuity. Refineries are reported to be operating at high capacity with adequate inventories of petrol and diesel, and domestic LPG production has been increased to support consump..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement