Smart City work near Caculo Mall may miss May 31 target
SMART CITIES

Smart City work near Caculo Mall may miss May 31 target

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji.

According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a "little longer" to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek.

Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress.

IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway.

IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji. According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a little longer to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek. Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress. IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway. IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement