Smart City work near Caculo Mall may miss May 31 target
SMART CITIES

Smart City work near Caculo Mall may miss May 31 target

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji.

According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a "little longer" to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek.

Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress.

IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway.

IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

The Imagine Panaji Smart City Development (IPSCDL) seems to be considering skipping the smart road work from Caculo Mall to the Tonca sewerage treatment plant (STP) due to practical challenges, despite the May 31 deadline for completing all ongoing smart city work in Panaji. According to IPSCDL, the cumulative target for completing all road works and making the road functional is May 31. However, they mentioned that this particular stretch might take a little longer to finish. IPSCDL stated that major challenges have been encountered in drilling due to the depth of sewerage works along the stretch, which is nearly 8 meters below road level and below the bed of the St Inez creek. Out of the total 430 metres, the main trunk pipeline of 300 meters has been laid, and work on the remaining 130 meters, which passes under the St Inez creek and connects to the Tonca STP, is currently in progress. IPSCDL added that along this stretch, one out of nine manholes has been completed, and another one is in progress. IPSCDL, led by its CEO Sanjit Rodrigues, is monitoring the ongoing sewerage work on the stretch on an hourly basis to meet the May 31 deadline. Regarding the stretch from the Four Pillar junction to the Old Patto bridge, the contractor appointed by IPSCDL has completed all major sewerage works, including laying a total pipeline of 1,400 meters, constructing 40 manholes, and installing 80 house connection chambers. Only one inter-connection is pending, which is expected to be completed in a couple of days. Currently, road restoration work is underway. IPSCDL mentioned that road construction on this stretch for the smart road project can only commence after the Public Works Department (PWD) finishes installing new pumping lines to connect pump houses located at Mala, near Bhandari hospital, and near the income tax office.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?