K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project
RAILWAYS & METRO RAIL

K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).

This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'

The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.

The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

Next Story
Infrastructure Energy

BMW Industries partners with IOCL for PNG supply at Bokaro plant

BMW Industries has entered into a strategic partnership with Indian Oil Corporation (IOCL) for the supply of Piped Natural Gas (PNG), reinforcing its commitment to adopting cleaner and more efficient energy sources for its operations.The agreement was signed at the Eastern Region Pipelines (ERPL) headquarters in Kolkata. The partnership is expected to support the company’s upcoming manufacturing facility in Bokaro by facilitating the use of natural gas as a primary energy source.According to the company, the adoption of PNG will help enhance operational efficiency while also contributing to ..

Next Story
Real Estate

Bombay Realty Secures RERA for Three ICC Tower in South Mumbai

Bombay Realty, the real estate arm of Bombay Dyeing and part of the Wadia Group, has received Real Estate Regulatory Authority (RERA) certification for Three ICC – Wing A, the latest luxury residential tower at Island City Center in Mumbai’s Dadar.The RERA registration marks a key milestone in the development timeline and reinforces the company’s focus on regulatory transparency, timely project delivery, and high construction standards.Following the success of One ICC and Two ICC, the upcoming Three ICC tower represents the next phase of the Island City Center development. The project ai..

Next Story
Infrastructure Energy

Flender launches India’s largest wind gearbox test rig in Walajabad

Flender has inaugurated a 13.5 MW wind turbine gearbox test rig at its Walajabad facility near Chennai, marking the largest installation of its kind in India. The new facility is expected to strengthen the company’s manufacturing and testing capabilities while supporting the growing demands of the wind power sector in both domestic and global markets.The test rig was inaugurated on March 5 in the presence of Andreas Evertz, Group CEO, Flender; Lars Wiegemann, Vice President Wind Gears, Flender; and Vinod Shetty, CEO, Flender India, along with key industry customers and stakeholders.The insta..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement