K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project
RAILWAYS & METRO RAIL

K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).

This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'

The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.

The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

Related Stories

Gold Stories

Next Story
Products

Interio by Godrej launches modular workplace solutions

Interio by Godrej has launched Workscapes, a modular workplace solutions category designed to help organisations configure and adapt workspaces to changing requirements. The portfolio combines mobile and compatible furniture and support elements that can be rearranged across different work modes without changes to fixed layouts.Workscapes includes Collaboration Tables, Privacy Solutions, Mobile Markerboards and Space Dividers, Power Solutions, Storage and Support Elements, Meeting and Presentation Tools, and Seating Elements. The range is designed for focused work, collaboration, informal disc..

Next Story
Infrastructure Urban

CAFE-III Gives Auto Industry Investment Clarity

The government’s new Corporate Average Fuel Economy (CAFE-III) norms have provided the automobile industry with a clearer framework for technology investments, according to industry representatives. The framework seeks to balance environmental objectives with flexibility for manufacturers while encouraging the adoption of flex-fuel vehicles and biofuels. Society of Indian Automobile Manufacturers (SIAM) President Shenu Agarwal said the five-year framework would give automakers greater predictability to plan investments and accelerate innovation. He said the regulation established annual targ..

Next Story
Infrastructure Energy

Mines Ministry to Auction Two Offshore Mineral Blocks in Andaman Sea

The Ministry of Mines will launch an auction of two offshore mineral blocks in the Andaman Sea on Thursday, seeking to unlock India’s offshore mineral potential and strengthen long-term mineral resource security. The blocks will be offered under a composite licence, which permits exploration and development activities in accordance with the applicable regulatory framework. The ministry said the auction was intended to encourage systematic exploration, attract investment and promote the use of advanced technologies for offshore mineral exploration and development. The initiative is also aimed..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code