K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project
RAILWAYS & METRO RAIL

K-RIDE to Invite Fresh Tenders for Bengaluru Suburban Railway Project

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).

This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'

The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.

The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

The 10-member K-RIDE board, chaired by Chief Secretary Shalini Rajneesh, has decided to invite fresh tenders for the completion of civil work on two stalled corridors of the Bengaluru Suburban Railway Project (BSRP), Corridor 2 (Benniganahalli-Chikkabanavara, 25.01 km), and Corridor 4 (Heelalige-Rajanukunte, 46.88 km).This decision follows the termination of contracts with L&T, the initial contractor for both corridors, due to disputes over delays and incomplete work. L&T had claimed Rs 505 million in damages and initiated arbitration proceedings in August after only 49.44 per cent of the work front was made available, with many sections deemed 'unworkable.'The Bengaluru Suburban Railway Project, which aims to complement Namma Metro, had originally been slated for completion within 40 months, as per a June 2020 deadline set by Prime Minister Narendra Modi. However, due to coordination issues between Karnataka and the Indian Railways, progress has been slow, with physical work at just 18.5 per cent completion as of March.The fresh tenders for Corridor 2 will be issued in three packages (Chikkabanavara-Yeshwantpur, Yeshwantpur-Hebbal, and Hebbal-Benniganahalli) in the coming days, with the work order expected by December. Tenders for Corridor 4 will be invited in November, with contracts likely awarded by early next year.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App